Tuesday, January 4, 2011

Tennessee Brownfield Toolbox

In 2009, the Tennessee Department of Environment and Conservation (TDEC) created the Brownfields Redevelopment Toolbox in conjunction with the Association of State and Territorial Solid Waste Management Officials (ASTSWMO) State Response Program and Brownfields Operation Task Force. 

The purpose of the Toolbox is to explain the Brownfields process in straightforward terms, and provide rural and smaller city governments/entities/communities with a systematic, start-to-finish, guide to Brownfields redevelopment. The Toolbox identifies five (5) steps in the Brownfields renewal process. The Toolbox provides a brief summary of each step, answers a series of Frequently Asked Questions (FAQs), and lists and summarizes available state and federal tools and incentives local governments may want to utilize in pursuing redevelopment of a Brownfield site in their community. A list of questions is presented at the end of Steps 1 through 3; based on the answers, the reader/user is directed to the appropriate next step for that project.

Here's a LINK.

Monday, January 3, 2011

Environmental Insurance for Brownfield Redevelopment

What is environmental insurance?

Environmental Insurance refers to a suite of insurance products designed to protect the insured (e.g., the developer, the remediation contractor) from cost overruns associated with environmental cleanup projects. The insurance is in addition to the general liability insurance typically carried by remediation firms and is particularly important for contractors on performance based contracts because they are paid for successful completion of milestones, not based on the level of effort to achieve those milestones. If an unexpected condition arises that drives the cost of the cleanup beyond what was originally anticipated and proposed, the insurance can provide the necessary funds to complete the work, up to the agreed upon spend limit.

What is the purpose of environmental insurance coverage?


The developer benefits from minimizing the impact of cost overruns through use of environmental insurance. This has the effect of limiting the overall cost risk to both the developer and contractors. In certain circumstances, without insurance, contractors might have to include very high contingencies and the overall cost to the developer might be prohibitively high. If insurance is used and the contractor encounter unanticipated contamination levels, extent, or constituents, or should the contractor have difficulties in the field, instead of the developer funding subsequent contract modifications, the contractor is required to seek insurance payment in order to cover the additional costs.


What sort of coverage does the insurance provide?

The insurance provides coverage for cost overruns - project costs that exceed the amount estimated in the project contract. The most common type of policy that protects against cost overruns above the estimated cost of remediation is Remediation Stop Loss Insurance (also known as Cleanup Cost Cap Insurance). The cost overruns covered by these policies are generally due to one of three occurrences:

* Regulatory or requirement changes;
* The discovery of new contaminants, or more extensive contamination, not identified when the remediation plan was designed; or
* Delays and difficulties in the execution of the original remediation plan.

The carrier issuing the policy indemnifies the insured for remediation costs above the estimated costs, plus an additional retention level, up to the policy cap. For example, a $1 million cleanup may require a $100,000 retention amount. In this simplified example coverage under the policy begins after $1.1 million (value of contract award plus retention amount) has been spent on the covered remediation project. If remediation costs exceed the insured amount, the additional costs revert back to the insured.

Why should a developer pay for insurance policies?

The insurance policy allows contractors to take on a greater amount of risk at a reduced cost to the developer. The developer is willing to pay the insurance premium because of the reduced remediation cost, the ability to cap remediation funding required to complete work at an installation, and because of the additional funding available via accessing the insurance policy should unforeseen circumstances arise.

How can the developer determine whether environmental insurance will be required?

Several factors are incorporated into the decision on whether to require environmental insurance on a project. These include the nature and scope of the work anticipated on the contract (e.g., groundwater remediation versus installation of a pre-approved cap design), the level of uncertainty remaining on a project, and whether the work will be conducted by a large or small business. In addition, the developer should carefully examines all aspects of the anticipated scope of effort to determine if there are some elements of the work that should not require environmental insurance. Such elements include long-term management of landfill caps and covers and development of the Project Management Plan.


How much does the insurance typically cost?

Policy premiums for the required insurance are based on a percentage of the guaranteed costs in combination with the limits of the policy, generally falling between 10% and 15% of the proposed remediation project cost.

Are the policy premiums considered a "remediation cost" under State Brownfield Tax Credit criteria?

Contact your State Brownfield Coordinator to determine whether policy premiums can be offset with a brownfield tax credit.

Sunday, January 2, 2011

EP Magazine: Vapor Intrusion and ASTM's Revised Vapor Encroachment Standard

FROM EP MAGAZINE - The experts answer why the topic is so hot now and the best way you can protect your clients and yourself from liability.

* By Dianne P. Crocker
* Dec 06, 2010

By now, you’ve probably heard about the indoor air quality issue that develops when rapidly evaporating chemicals from polluted soil or groundwater make their way into indoor air. If not, you soon will — a spate of lawsuits, increased regulatory interest, and a recently revised ASTM screening standard have converged in a short period of time to bring the issue to the fore and effectively change due diligence best practices.

[MORE]

Saturday, January 1, 2011

Brownfield Tip of the Month (January) - Field a Strong Brownfield Team with Leadership from the Top

Brownfield success is about people. Localities most successful in brownfield revitalization have set up
brownfield teams that include prominent local leaders, a brownfield staff champion, and a cross-sector
team of public and private supporters. The use of a well rounded local government team for
brownfields can help the prospective end-users of these sites overcome the tough barriers to
brownfield redevelopment. A local brownfield team can also bring together the cross-disciplinary
skills necessary to address these complex environmental, economic and social challenges. In addition,
the establishment of the right team helps ensure that the community's brownfield initiatives are
sustained beyond the expiration of EPA brownfield grant funding or other start-up funding that
launched these programs. A local brownfield team should include the following.

Leadership from Top Local Officials

Whether from the Mayor, City Council, City Manager, County Supervisor or a top agency official, the
nation's top brownfields programs all receive leadership from high-ranking local officials. These officials
are essential to providing the vision, building the community support, developing the partnerships, and
obtaining the resources needed for a successful program. They also bring the private sector to the
table, lobby for funding, testify in Congress, and speak at conferences to demonstrate their leadership.
For example:

-Chicago Mayor Richard Daley has committed more than $70 million to establish an
aggressive local program that acquires and prepares brownfields properties for commercial
and industrial redevelopment.

-Tom Suozzi, the former Mayor of Glen Cove, New York who was recently elected as
County Executive for Nassau County, made the revitalization of the brownfields on Glen
Cove's waterfront his top community priority. He is now implementing an ambitious
brownfields program for the entire County.

-Mayor Dan Malloy of Stamford, Connecticut has made the revitalization of his City's Mill
River Corridor his top economic development priority. By becoming a national spokesman
on brownfields, Mayor Malloy has leveraged more than $50 million in state and federal
funding for land acquisition, transportation, affordable housing, greenway development,
and other priorities that are components of his revitalization plans.


Interagency Team

Most successful brownfield programs have established local interagency teams, which serve several
valuable functions. Different agencies bring the different skills and areas of expertise required for
revitalization. By having all of the relevant agencies involved, the locality can create greater
predictability in the development process and thereby enhance its credibility with the private sector.
Moreover, the participation of multiple agencies provides a variety of entry points for property owners
and developers interested in redeveloping brownfields. There are a number of different models for
interagency teams, but virtually all have participation from at least the Mayor's office and the economic
development, environmental, planning, finance, and legal departments. Many also include the local
parks, public works, public health, housing, buildings and transportation departments. For example:

In Chicago, the Mayor's Office has a point person who helps coordinate a team of senior
officials from the departments of Planning and Development, Environment, Management and
Budget (OMB) and Law. Planning and Development takes the lead in identifying the priority
sites and negotiating the deals. Environment makes sure sites are properly assessed and cleaned
up. OMB helps identify and secure funding. Law makes sure the deals can happen. In addition,
the departments of Transportation and Buildings are often involved, depending on the specific
project.

The City Manager's office in Phoenix, Arizona established an interdepartmental Brownfields
Task Force, consisting of representatives from nine city departments, to develop a formal
program to encourage brownfields redevelopment by the private sector in Phoenix. City
Council also unanimously approved establishment of the program with funding from the City's
general funds and bond budgets.

Lawrence, Massachusetts tackled this problem by establishing two interagency task forces —
teams comprised of local, state, and federal representatives — that ironed out key issues,
facilitated decision making, and coordinated the multiple regulatory issues connected with
brownfields projects.

This interagency approach is key to brownfields success, because bureaucracy at the local level can kill
brownfields projects. Many brownfield projects are burdened by high assessment and remediation
costs and by long, drawn-out time frames — a situation that is only exacerbated when multiple
government agencies are involved. An interagency team can promote one-stop-shopping for
brownfields parties to help avoid these brownfields barriers.

It is important to emphasize that interagency coordination can yield important benefits that don't
require any cash outlay by the city. In several cases, streamlining interagency coordination was critical
in resolving overlaps in administrative jurisdictions and oversight. It saved the city staff resources, and
the developer valuable time. Cities like Dallas, Texas and Detroit, Michigan have used a brownfield
"SWAT Team" approach, pulling people from different departments like planning and public works into
a single brownfield unit. They can quickly deal with all types of situations that can come up in a
brownfield reuse project. Moreover, this kind of approach has been replicated in small cities, like in the
Southwest Municipal Conference consortium in Cook County, Illinois. There, officials from several
communities have joined forces to identify experts from within the different cities, the county, and
from around the state who they can call in when specific brownfield situations arise.

Local Brownfield Staff

Most successful programs devote some local staff to implementing their brownfields programs. Many,
like Kansas City, Missouri; Phoenix, Arizona; and Nashville, Tennessee have at least one full time point
person (usually a "Brownfield Program Manager" or "Brownfield Coordinator") assigned to spend all
of their time and energy leading and coordinating the effort. Others, like Chicago, Illinois have several
staff that are part of the brownfields team, and each devotes substantial time to brownfields projects.
Dedicated brownfields staff can also help overcome a common problem for most localities, namely,
that no single office or entity is responsible for overseeing brownfields projects. Instead, myriad players
from a range of departments must be coordinated, creating an administrative nightmare. All agree that
establishing a single entity for oversight of brownfield initiatives is key. The Worcester Redevelopment
Authority (WRA) in Worcester, Massachusetts is an example of such a framework. The WRA acquires
properties, coordinates remediation, and facilitates site redevelopment work — acting as a
"brownfields broker." Similarly, the Port of Seattle assembled under one lead manager a group of staff
members who were dedicated to the Southwest Harbor redevelopment project. This team, which
worked out of one office location, included members of the port's marine facilities as well as staff from
legal, engineering, environmental, and finance offices.

Small and rural communities that may not have the resources to dedicate local staff to brownfields can
explore collaborative approaches with other communities. For instance, a number of small
communities could join together to hire expert staff assistance to work with all of the participating
towns. Such staff could also be funded through regional planning and economic development agencies.
For example, in the Asheville, North Carolina area, the Land-of-Sky Regional Council used EPA,
Economic Development Administration, Appalachian Regional Commission, and other funding to
organize a regional plan to revitalize brownfields and spark economic development across a region that
includes four counties and 15 cities and towns. Four specific brownfield redevelopment projects are
already underway since the effort began in 1998.

Technical Expertise

The best local brownfields teams will make use of people with technical expertise in brownfields issues.
With local technical expertise in assessment, cleanup, redevelopment planning, funding, permitting and
other key issues, a community can facilitate both public and private sector revitalization. This approach
can save time, money and uncertainty for the parties involved in a brownfields project. In larger
localities with greater resources and a number of brownfields projects, this expertise can be brought in
house onto the local staff. In smaller communities or areas with a more limited number of brownfields,
the locality can contract technical expertise with experience in local brownfields revitalization (and,
this could potentially be funded by EPA assessment grants). In some regions, localities have joined
together to fund and share technical personnel who can then act as "brownfield circuit riders" among
various communities. See, e.g. the Indiana Association of Cities and Towns, Environmental Circuit
Riders program at www.citiesandtowns.org/content/member_resources/environment_DHT.htm.